After our successful installation and completion of the contract at the Rotherhithe Tunnel, this is an extract from the TFL monthly news bulletin:
"The P&M ELTRACs team have just completed a 21 week programme of modernising the Rotherhithe emergency telephone system, including all cabling, over 3000 meters of trunking, all conduit drops to the new telephones, and a brand new 36 fibre (4km) installation spliced at each vent shaft as a resilience measure. 21 weeks sounds a long time but when you consider we only have about 5 hours per week that’s only 105 hours in total. The programmmes of works were not only completed on time, but also in budget."